The challenge, our approach and progress made
Challenge
There are currently no trails in the Eden or across the Yorkshire Dales National Park that are planned (and promoted) specifically for those who have sensory impairments (there are very few in the north of England with the nearest being Harrogate) and a limited number of fully accessible trails (only five with this level of accessibility promoted within the whole Yorkshire Dales National Park and one in the north of the Eden catchment at Talkin Tarn.)
Approach
To increase the number of places in the Eden where those with sensory and physical challenges can experience nature on their own terms.
Progress highlights last quarter: Apr 2026 - Jun 2026
- Paula, new Community Engagement Officer with the Yorkshire Dales National Park Authority, started on 27th April and has completed her induction.
- Outreach work to identify key organisations and individuals is already well underway. A meeting with The Sensory Trust has also been held to discuss support and consultancy for development of the Podgill Sensory Trail.
- Planning permission for the bridges has been received and the project is on track to be delivered for September 2026.
Progress highlights to date: Apr 2024 - Mar 2026
- All aggregate work complete other than the bridge ends.
- The gates at the eastern end of the accessible path have been installed.
- Initial consultation meeting held with Sensory Trust about the sensory trail at Podgill and agreement in principle with landowner to develop ideas secured.
- Community Engagement Officer has been appointed, to start 27th April.
- Surfacing works at Smardale commenced in early November 2025, with the path tray excavated, followed by application of sub-base and a top-dressing of limestone.
- Bridge structures have been purchased!
- A Biodiversity Net Gain assessment has been completed.
- A badger survey has been completed. It contains recommendations to build into the works methodology.
- The next step is the planning application submission. The build and installation of bridges and the surfacing works are now scheduled for August or September 2025.
- A full planning application has been submitted for improvements to 1.5km of disused railway track bed, including the creation of an accessible path and installation of two new footbridges where the route crosses public roads. The path works will be completed in advance, as the bridges will be assembled on the track bed before being moved into position.
- To help expedite delivery, the Yorkshire Dales National Park Authority (YDNPA) confirmed that the path enhancement works could proceed as permitted development and began in October 2025.